NORTH COAST – Caltrans reports that the following road projects will be taking place around Lake County during the coming week.
Included are Mendocino County projects that may impact Lake County commuters.
LAKE COUNTY
Highway 20
– Construction of a roundabout at the Route 20/Nice-Lucerne Cutoff Road intersection will continue. Temporary all-way stop signs are in place. A shoulder closure will be in effect 24 hours per day, seven days per week. Motorists are advised to drive with caution through the area and may experience minor traffic slowdowns. Nice-Lucerne Cutoff Road is closed at Route 20; a detour is available. Contractor – Granite Construction Inc. of Ukiah.
– PG&E of Ukiah has been issued a Caltrans Encroachment permit for utility work from Island Drive to Shady Lane. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 5-minute delays.
Highway 53
– Pavement repairs from Wilson Street to 40th Avenue will continue. Nighttime work hours are 10 p.m. to 7 a.m., Sunday evening through Friday Morning. One-way traffic control will be in effect, and motorists should anticipate five-minute delays. Daytime work hours are 7 a.m. to 5 p.m., weekdays. A shoulder closure will be in effect, and motorists are advised to drive with caution through the area and may experience minor traffic slowdowns. Contractor – Teichert Construction of Davis.
– Highway widening and rehabilitation from 40th Avenue to the junction of Routes 20/53 will continue. Work hours are 6:30 a.m. to 5:30 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Teichert Construction of Davis.
MENDOCINO COUNTY
Highway 1
– AT&T of Fort Bragg has been issued a Caltrans Encroachment permit for utility work near Creamery Lane beginning Tuesday, Sept. 4. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
– Replacement of the Greenwood Creek Bridge will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate five-minute delays. Contractor – Golden State Bridge Inc. of Martinez.
– The city of Fort Bragg has been granted a Caltrans Encroachment Permit to hold the Paul Bunyan Days Labor Day Parade between Madrone Avenue and Elm Street on Monday, Sept. 3. Event hours are 9 a.m. to noon. A full road closure will be in effect. A detour will be available.
Highway 20
– A pavement repair project from Forestry Station Road to Three Chop Road will continue. Work hours are 6 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
– Paulson Excavation of Albion has been issued a Caltrans Encroachment permit for fuel spill cleanup 1.3 miles east of Three Chop Road. Work hours are 7 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays.
– A pavement repair project from Road 300 to Three Chop Road will continue. Work hours are 6 a.m. to 3 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Granite Construction of Ukiah.
Highway 101
– Caltrans will perform slide repairs near the Korean War Veterans Memorial Bridge (near Frog Woman Rock). Northbound traffic will be restricted to one lane 24 hours per day, seven days per week. Motorists may experience minor traffic slowdowns.
– Crosswalk improvements at Gregory Lane will continue. Work hours are 5 a.m. to noon, weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns. Contractor – Cal Electro Inc. of Redding.
– Shoulder widening and installation of rumble strips from just north of Ryan Creek Road (south) to just south of Big Trails Drive will continue. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Legg Inc. of Livermore.
Highway 128
– PG&E of Ukiah has been issued a Caltrans Encroachment permit for utility repairs from Philo Greenwood Road to Indian Creek. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
– Paving from Con Creek to Robinson Creek will continue. Work hours are 6 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
– Pavement repairs from 1.9 mile west of the Ornbaun Creek Bridge to 0.3 mile west of Elkhorn Creek will continue. Work hours are 6 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – OC Jones and Sons of Berkeley.
Highway 175
– Beckstoffer Vineyards of Talmage has been granted a Caltrans Encroachment Permit to pave a commercial driveway beginning Tuesday, Sept. 4. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
Highway 253
– Metal beam guardrail repair at various locations from Singley Cattlepass to Robinson Creek Road will continue. Work hours are 7 a.m. to 7 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. Contractor – Coral Construction of Wilsonville.
– Culvert repairs at various locations from Cattle Pass to 0.5 mile west of Slide Creek will continue. Work hours are 6 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. Contractor – Team Ghilotti of Petaluma.
– Slipout repairs about 5.6 miles west of Butler Ranch will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate five-minute delays. Contractor – Mendocino Construction Services of Willits.
Work on all these projects is weather permitting and subject to change. Caltrans advises motorists to drive with caution when approaching work areas and to be prepared to stop at traffic control stations.
The Caltrans Traffic Operations Office has reviewed each project and determined that individual project delays are expected to be less than the statewide policy maximum of 30 minutes, unless noted otherwise above.
For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).