NORTH COAST – Caltrans reports that the following road projects will be taking place around Lake County during the coming week.
Included are Mendocino County projects that may impact Lake County commuters.
LAKE COUNTY
Highway 20
– A highway widening project from Polk Jones Cattlepass to Nice-Lucerne Cutoff Road will continue. Work hours are 7 a.m. to 2 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
– Mediacom of Clearlake Oaks has been granted a Caltrans Encroachment Permit for a cable crossing on Tuesday, Oct. 21, from 7 a.m. to 3 p.m. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
– A roadway realignment project from 1.4 miles east of the North Fork Cache Creek Bridge to 1.6 miles west of Walker Ridge Road will continue. Work hours are 7:30 a.m. to 6 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 20-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
Highway 29
– Bridge rehabilitation from the Adobe Creek Bridge to the Park Way Overcrossing will continue. Work hours are 7 p.m. to 7 a.m., Monday night through Friday morning. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – American Civil Constructors of Benicia.
MENDOCINO COUNTY
Highway 1
– A paving project from Walnut Street to Pudding Creek Road will continue. Work hours are 7 a.m. to 5 p.m., weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns. Contractor – Argonaut Constructors of Santa Rosa.
– The City of Fort Bragg has been granted a Caltrans Encroachment Permit to install a new sewer line between Elm Street and Airport Road. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
Highway 20
– A highway widening project from Old Willits Road to Gravel Pitt Road will continue. Work hours are 7 a.m. to 3 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 20-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
Highway 101
– A pavement repair project from 0.1 miles north to 1.5 miles north of Comminsky Station Road will continue. Northbound traffic will be restricted to one lane 24 hours per day, seven days per week. Motorists may experience minor traffic slowdowns.
– A paving project from Center Street to the junction of Route 101/253 will continue. Work hours are 7 a.m. to 5 p.m., weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns. Contractor – Martin Brothers Construction of Sacramento.
– Roadway repair due to pavement deterioration from 3.6 miles south of Ridgewood Ranch Road to 1.9 miles south of Ridgewood Ranch Road will continue. Traffic will be restricted to one lane in each direction of travel 24 hours per day, seven days per week. Motorists may experience minor traffic slowdowns.
– Bridge deck rehabilitation on the South Willits Overhead will continue. Traffic will be restricted to one lane in each direction of travel 24 hours per day, Monday through Friday. Motorists may experience minor traffic slowdowns. Contractor – American Civil Constructors of Benicia.
– The City of Willits has been granted a Caltrans Encroachment Permit to install a water main between California Street and Commercial Street. Work hours are 7 a.m. to 4 p.m., weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns.
– Bridge deck rehabilitation on the Long Valley Creek Bridge will continue. Traffic will be restricted to one lane in each direction of travel 24 hours per day, Monday through Friday. Motorists may experience minor traffic slowdowns. Contractor – American Civil Constructors of Benica.
Highway 162
– Bridge deck rehabilitation on the Long Valley Creek Bridge will resume. Work hours are 7 p.m. to 7 a.m., Monday evening through Friday morning. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – American Civil Constructors of Benicia.
– A bridge widening project at Outlet Creek Bridge will continue. One-way traffic control with a temporary signal is in effect 24 hours per day, seven days per week. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.
– Caltrans will perform routine maintenance from the South Eel River Bridge to Laytonville Dos Rios Road beginning Monday, Oct. 20. Work hours are 8:30 a.m. to 3:30 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
Highway 253
– A bridge widening project at Anderson Creek Bridge will continue. One-way traffic control with a temporary signal is in effect 24 hours per day, seven days per week. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.
– A bridge widening project at Soda Creek Bridge will continue. One-way traffic control with a temporary signal is in effect 24 hours per day, seven days per week. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.
For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).
{mos_sb_discuss:2}