NORTH COAST – Caltrans reports that the following road projects will be taking place around Lake County during the coming week.
Included are Mendocino County projects that may impact Lake County commuters.
LAKE COUNTY
Highway 20
– A roadway realignment project from 1.4 miles east of the North Fork Cache Creek Bridge to 1.6 miles west of Walker Ridge Road will continue. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
Highway 29
– A slide repair project from the Lupiyoma Creek Bridge to Bar X Ranch will continue through Friday, Jan. 16. Work hours are 7 a.m. to 3 p.m., weekdays. A shoulder closure will be in effect with intermittent one-way traffic control. Motorists should anticipate five-minute delays. Contractor – Argonaut Constructors of Santa Rosa.
Highway 281
– Caltrans will continue routine maintenance from 0.9 miles west of Tenino Way to the junction of Route 29/281. Work hours are 8:30 a.m. to 3:30 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays.
MENDOCINO COUNTY
Highway 1
– AT&T of Sacramento has been granted a Caltrans Encroachment Permit for utility work from Lake Street to 0.2 miles south of Stonebord Road beginning Tuesday, Jan. 20. Work hours are 9 a.m. to 2 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.
Highway 101
– A pavement repair project from 0.1 miles north to 1.5 miles north of Comminsky Station Road will continue. Northbound traffic will be restricted to one lane 24 hours per day, seven days per week. Motorists may experience minor traffic slowdowns.
– Roadway repair due to pavement deterioration from 3.6 miles south of Ridgewood Ranch Road to 1.9 miles south of Ridgewood Ranch Road will continue. Traffic will be restricted to one lane in each direction of travel 24 hours per day, seven days per week. Motorists may experience minor traffic slowdowns.
– PG&E of Ukiah has been granted a Caltrans Encroachment Permit for utility work at Oak Creek Avenue on Friday, January 16 from 9 a.m. to 3 p.m. Traffic will be restricted to one way each direction of travel. Motorists should anticipate minor traffic slowdowns.
Highway 128
– AT&T of Walnut Creek has been granted a Caltrans Encroachment Permit for utility work from 1.5 to 2.5 miles east of Dry Creek Bridge. Work hours are 7 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays.
Highway 162
– A bridge widening project at Outlet Creek Bridge will continue. Work hours are 7 a.m. to 5 p.m. weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.
Highway 253
– A bridge widening project at Soda Creek Bridge will continue. Work hours are 7 a.m. to 5 p.m. weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. Contractor – Viking Construction Co. Inc. of Rancho Cordova.
For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).